Granular Base Stabilization with Emulsion in Las Vegas, Nevada
Authors
Chris Finberg, Dan Quire and Todd Thomas
Summary
Washington Ave. in Las Vegas, Neveda was distresses such that reconstruction was needed. The existing pavement consisted of 4.5 to 7 inches of asphalt pavement over 13.5 to 18.5 inches of granular base. The conventional design would have consisted of removal of the asphalt and base material and replacement with 18 inches of granular base and 6 inches of asphalt. An alternative method was selected using base stabilization with emulsified asphalt. The alternate design consisted of removal of the asphalt pavement and in-place stabilization with 5% emulsified asphalt of the upper 6 inches of the existing base followed by 5 inches of new asphalt. The alternate design saved the city an estimated $323,000, a 30% savings. Construction days were reduced from an estimated 120 days to 40 days and 3,000 fewer loads of materials were trucked on and off the project.
Citations
Paper No. 08-2343.TRB 87th Annual Meeting Compendium of Papers DVD. Transportation Research Board, Washington, DC, January 2008.
Let's Connect
Get the latest in industry trends, research, success stories, and technical updates in a succinct e-newsletter.
PPRA Industry News Signup
Thank you!
Thank you for signing up for the PPRA mailing list!
If you created an account, you should receive an email shortly with more instructions to activate your account.