The information provided herein should be considered as guidelines, and are intended to be used in conjunction with the appropriate documents. Acceptance of CP operations are primarily based on, but not always limited to, the items listed below. For ARRA resources and detailed information on Acceptance Criteria, please refer to  The Basic Asphalt Recycling Manual, the ARRA Construction Guidelines CP101 and CP102. Suggested mitigation for non-compliance are indicated in the Troubleshooting Section and the Basic Asphalt Recycling Manual.


Acceptance Guidelines

Surface Texture

Pavement surface should be tested for milling texture in accordance with AARA CP101 for standard milling and CP102 for micro milling.

Surface Tolerance

The finished surface and grade of the milled pavement should be checked regularly during milling using a 10 ft. (3 m) straight edge. The straight edge may be placed in any direction on the surface except across the crown.

Milling Depth or Cross-Slope

Check the pavement surface for either milling depth or cross-slope. You cannot mill to a constant depth and cross-slope.