Proposed AASHTO Practice and Tests for Process Control and Product Acceptance of Asphalt-Treated Cold Recycled Pavements

Authors

Diefenderfer, Boz, Habbouche, Jones, Hand, Bowers & Flintsch

Summary

This is the final report for NCHRP 9-62 project where the authors developed a short pin raveling test to determine when a CIR pavement has sufficiently cured to allow opening to traffic and a long pin test to determine when the pavement has cured sufficiently to place the wearing surface. The authors have recommended additional field verification of the proposed test methods and threshold values. 

Citations

NCHRP Research Report 960. Transportation Research Board, Washington, D.C., 2021.