Soil Stabilization & Soil Modification

Find a Contractor/Supplier

Application Sequence

IN-PLACE APPLICATIONS  

  1. Apply dry chemical modifying/stabilizing agents using a calibrated bulk spreader/distributor
  2. Chemical modifying/stabilizing agents applied as slurry can be spread ahead of mixing passes using a calibrated liquid distributor or added during the mixing pass of the reclaimer using the reclaimer’s on-board additive system 
  3. Add bituminous stabilizing agents during the mixing pass of the reclaimer using the reclaimer’s on-board additive system
  4. Apply water during pulverization and mixing passes to the stabilized subgrade material as required to activate chemical stabilizing agents and aid in proper compaction. Water may be added using water trucks or through the reclaimer’s on-board additive system 
  5. Compact the stabilized subgrade material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers 
  6. Shape/trim the stabilized subgrade to the required cross-slope and grade
  7. Minimumize vehicular traffic on stabilized subgrade for 30 to 60 minutes
  8. Allow the stabilized subgrade to properly cure
  9. Apply the remaining pavement structure

Central Plant Applications

  1. Feed soil and modifying/stabilizing agent into the mixing plant
  2. Transfer the modified/stabilized mix to the site in haul trucks
  3. The modified/stabilized mix is either placed in a windrow on the subgrade and spread with a motor grader or placed into a paver or aggregate spreader using  a windrow elevator or placed directly into the paver or aggregate spreader hopper.
  4. Compact the modified/stabilized material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers 
  5. Shape/trim the modified/stabilized material to the required cross-slope and grade
  6. Minimumize vehicular traffic on modified/stabilized material for 30 to 60 minutes
  7. Allow the modified/stabilized mixture to properly cure
  8. Apply the wearing surface

Soil Stabilization: For cementitious additives smooth drum rolling should be completed within 2 hours of spreading material to achieve maximum results.


Application Guidelines

Medium bulker
Pneumatic Tank Truck

Control Strip

  • If required, a control strip should be placed at the beginning of the project to evaluate the equipment, construction methodology, workmanship and to verify that the construction process meets specification requirements

 

Medium terra gator
Spreader Truck

Application of Dry Modifying/Stabilizing Agents

  • If added at a central plant verify application rates using meter on plant
  • Dry chemical modifying/stabilizing agents can be added prior to the mixing pass of the reclaimer. 
  • Dry chemical modifying/stabilizing agents should be applied with non-pressurized mechanical vane-feed, cyclone or screw type bulk spreaders/distributors
  • Check application rates either volumetrically or by using a “canvas patch” test or similar procedure  

 

Medium water
Water Truck

Application of Modifying/Stabilizing Agents Applied as Slurry

  • Verify application rates of chemical modifying/stabilizing agents applied as slurry at a central plant using meter on plant
  • Chemical modifying/stabilizing agents applied as slurry can be spread ahead of mixing passes using a calibrated liquid distributor or added during the mixing pass of the reclaimer using the reclaimer’s on-board additive system. Application through the reclaimer generally results in a more uniform application 
  • Verify application of slurry modifying/stabilizing agents using the consumption of modifying/stabilizing agent (and water) obtained from the computer that controls the slurry mixing unit.

 

Medium tiller
Reclaimer

Application of Bituminous Stabilizing Agents

  • Verify application rates of bituminous stabilizing agents mixed at a central plant using meter on plant
  • Bituminous stabilizing agents applied during the mixing pass of the reclaimer using the reclaimer’s on-board additive system. 
  • Verify the application rate by evaluating the mass of stabilized material against the volume of stabilizing agent used for a single tanker.
  • For foamed asphalt stabilization, check the temperature of the asphalt before connecting a tanker to the reclaimer.
  • For foamed asphalt stabilization, verify the expansion ratio and half-life using the test nozzle on the reclaimer.

 

Medium compactor
Sheeps Foot Compactor

In-Place Mixing

  • Check depth of mixing by removing the modified/stabilized material on each side of the reclaimer/tiller and check the depth
  • Overlap longitudinal joints a minimum of 6 inches and transverse joints a minimum of 2 feet
Medium grader
Motor Grader

Compaction

  • Establish a rolling pattern to achieve the required percent compaction
  • Compact the modified/stabilized material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers 
  • The total time for mixing, placing and compacting cementitious stabilized materials should be less than 2 hours
  • Compaction requirements for cement stabilization are typically 95 to 98% of ASTM D588.
  • Modification and stabilization with hydrated lime or LKD is usually allowed to mellow prior to compaction
  • For modification/stabilization with quicklime, the materials are usually allowed to mellow for at least 12 hours after mixing and prior to compaction
  • Compaction requirements for Lime/LKD stabilization are typically based on standard Proctor, 95% of the maximum dry density
  • Check compaction with a nuclear gauge, sand cone or other approved method
  • Check cross-slope after final rolling 

 

Medium roller
Smooth Drum Roller

Curing

  • Stabilized materials need to be properly cured to achieve ultimate strength, prevent raveling and facilitate placement of the pavement structure
  • Minimize vehicular traffic on stabilized materials for 30 to 60 minutes 
  • Limit truck traffic until the stabilized material until the mix has cured sufficiently to support the anticipated traffic without damaging the stabilized mixture
  • For chemical stabilizing agents either keep the surface moist or apply a curing membrane to allow proper hydration and strength gain of the materials, typically 2-7 days

 

Pavement Structure

  • Prior to placing the first lift of the pavement structure sweep the stabilized mixture with a power broom.