IN-PLACE APPLICATIONS:Working with in-place aggregates or after adding imported aggregates to existing base layer
Apply dry chemical stabilizing agents using a calibrated bulk spreader/distributor
Add bituminous stabilizing agents during the mixing pass of the reclaimer using the reclaimer’s on-board additive system
Chemical stabilizing agents applied as slurry can be spread ahead of mixing passes using a calibrated liquid distributor or added during the mixing pass of the reclaimer using the reclaimer’s on-board additive system
Apply water during pulverization and mixing passes to the stabilized material as required to activate chemical stabilizing agents and aid in proper compaction. Water may be added using water trucks or through the reclaimer’s on-board additive system
Compact the stabilized material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers
Shape/trim the stabilized material to the required cross-slope and grade
Minimumize vehicular traffic on stabilized base material for 30 to 60 minutes
Allow the stabilized mixture to properly cure
Apply the wearing surface
Central Plant Applications
Remove any existing bound material to expose the base layer
Feed aggregate stabilizing agent and any additives into the mixing plant
Transfer the stabilized base mix to the site in haul trucks
The stabilized mix is either placed in a windrow on the subgrade and spread with a motor grader or placed into a paver or aggregate spreader using a windrow elevator or placed directly into the paver or aggregate spreader hopper.
Apply water, if necessary, and compact the stabilized material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers
Shape/trim the stabilized material to the required cross-slope and grade
Minimumize vehicular traffic on stabilized base material for 30 to 60 minutes
Allow the stabilized mixture to properly cure
Apply the wearing surface
Application Guidelines
Control Strip
If required, a control strip should be placed at the beginning of the project to evaluate the equipment, construction methodology, workmanship and to verify that the construction process meets specification requirements
Application of Dry Stabilizing Agents
If added at a central plant verify application rates using meter on plant
If adding new base material on site apply granular materials prior to mixing using a mechanical spreader, paver or by haul trucks and then spread to a uniform thickness with a motor grader
Dry chemical stabilizing agents can be added prior to the mixing pass of the reclaimer.
Dry chemical stabilizing agents should be applied with non-pressurized mechanical vane-feed, cyclone or screw type bulk spreaders/distributors
Check application rates either volumetrically or by using a “canvas patch” test or similar procedure
Application of Stabilizing Agents Applied as Slurry
Verify application rates of chemical stabilizing agents applied as slurry at a central plant using meter on plant
Chemical stabilizing agents applied as slurry can be spread ahead of mixing passes using a calibrated liquid distributor or added during the mixing pass of the reclaimer using the reclaimer’s on-board additive system. Application through the reclaimer generally results in a more uniform application
Verify application of slurry stabilizing agents using the consumption of stabilizing agent (and water) obtained from the computer that controls the slurry mixing unit.
Application of Bituminous Stabilizing Agents
Verify application rates of bituminous stabilizing agents mixed at a central plant using meter on plant
Bituminous stabilizing agents applied during the mixing pass of the reclaimer using the reclaimer’s on-board additive system.
Verify the application rate by evaluating the mass of stabilized material against the volume of stabilizing agent used for a single tanker.
For foamed asphalt stabilization, check the temperature of the asphalt before connecting a tanker to the reclaimer.
For foamed asphalt stabilization, verify the expansion ratio and half-life using the test nozzle on the reclaimer.
In-place Mixing
Check depth of mixing by removing the stabilized material on each side of the reclaimer and checking the depth.
Overlap longitudinal joints a minimum of 6 inches and transverse joints a minimum of 2 feet
Compaction
Establish a rolling pattern to achieve the required percent compaction
Compact the stabilized material to the required percent compaction using any combination of segmented padfoot, vibratory padfoot, rubber-tired, vibratory single or double drum rollers
Compaction requirements for Bituminous stabilization are typically based on 95% of the maximum dry density determined in accordance with AASHTO T 180 or ASTM D1557, modified Proctor
The total time for mixing, placing and compacting cementitious stabilized mixtures should be less than 2 hours
Compaction requirements for Cement stabilization are typically 95 to 98% of ASTM D588.
Stabilization with hydrated lime or LKD is usually allowed to mellow prior to compaction
For stabilization with quicklime, the materials are usually allowed to mellow for at least 12 hours after mixing and prior to compaction
Compaction requirements for Lime/LKD stabilization are typically based on standard Proctor, 95% of the maximum dry density
Check compaction with a nuclear gauge, sand cone or other approved method
Check cross-slope after final rolling
Curing
Stabilized materials need to be properly cured to achieve ultimate strength, prevent raveling and facilitate placement of the surface course
Minimize vehicular traffic on stabilized materials for 30 to 60 minutes
Limit truck traffic until the stabilized material until the mix has cured sufficiently to support the anticipated traffic without damaging the stabilized mixture
For chemical stabilizing agents either keep the surface moist or apply a curing membrane to allow proper hydration and strength gain of the materials, typically 2-7 days
Surface Course
A surface course is required over stabilized materials
Prior to placing the subsequent course sweep the stabilized mixture with a power broom. A fog or tack coat of emulsified asphalt may be required, depending on local practice.
Let's Connect
Get the latest in industry trends, research, success stories, and technical updates in a succinct e-newsletter.
PPRA Industry News Signup
Thank you!
Thank you for signing up for the PPRA mailing list!
If you created an account, you should receive an email shortly with more instructions to activate your account.